Project Management – Formule

PERT (program evaluation and review technique)
Prj Time Management: estimate activity duration – tools and techniques: Three-Point Estimates

  • PERT (Expected Activity duration): (P + (4*M) + O) / 6
  • Standard Deviation: (P – O) / 6
  • Variance: [(P – O)/6 ]squared

M=Most likely; P=Pessimistic; O=Optimistic.

*** *** *** *** ***

Communication Channels
Prj Communications Management: Plan Communications: Tools and Techniques

  • Total number of potential communication channels:  n(n-1)/2

n = number of stakeholders.

*** *** *** *** ***

Prj RiskManagement

  • Expected Monetary Value: Probability * Impact
Annunci
  1. Non c'è ancora nessun commento.
  1. No trackbacks yet.

Rispondi

Effettua il login con uno di questi metodi per inviare il tuo commento:

Logo WordPress.com

Stai commentando usando il tuo account WordPress.com. Chiudi sessione / Modifica )

Foto Twitter

Stai commentando usando il tuo account Twitter. Chiudi sessione / Modifica )

Foto di Facebook

Stai commentando usando il tuo account Facebook. Chiudi sessione / Modifica )

Google+ photo

Stai commentando usando il tuo account Google+. Chiudi sessione / Modifica )

Connessione a %s...

%d blogger hanno fatto clic su Mi Piace per questo: